PREORDERS AND GROUPBUYS

PRODUCT UPDATES

GROUPBUYS and preorders

Updated delivery time - November 2026

  • Magnets - ready
  • Feet - ready
  • Hardware - ready
  • CNCed parts - some ready, some in production
  • PCBs - ready
  • Silicone parts - some ready, some in production
  • Carrying case - in production
  • Injection molded tops - preproduction samples received and being confirmed for production
  • Torx sticks - ready

Now estimated to delivery in November 2026.

  • PCBs - ready
  • Plates - ready
  • Magnets - ready
  • Feet - ready
  • Housings - delayed, manufacturing issue. Resolution in progress.
  • Carrying case - in production

These are estimated to arrive to us Q4 2026 which spans October - December.

  • Housings - production queue
  • Plates - production queue
  • Bumpers - in production
  • Poron strips - in production
  • DynaPaks - ready
  • HE PCBs - on order with Geon
  • Hybrid PCBs - preproduction sample in testing
  • Carrying case - awaiting final sample to give final production green light

These are estimated to arrive to us Q4 2026 which spans October - December.

Ktechs is lead vendor on this project - status as of mid-August is in production.